What's Happening ?
SP Energy Networks are undertaking work to upgrade our electricity infrastructure in the area and as part of that we are investing £0.5 million to install 2.7 kilometres of new low voltage (LV) cable throughout Dirleton to modernise the network and improve resilience.
We know the community has experienced a significant number of faults and upgrading the LV network in Dirleton will improve network resilience. This work will also facilitate further connection of low carbon technologies as we transition towards Net Zero.
When's it Happening ?
April to October 2024
Contact Details for SP Energy Networks
Project Update Contact Details
Andrew Mitchell (Project Manager)
- 07717 546956
Chris Ryles (Assistant Project Manager)
- 07744 2934503
For Supply Issues and Emergencies ONLY
please call:
0800 092 9290
or
105
Further Details and Documents
As the project progresses there will be a collection of the SP Energy Networks documents and project updates on this page.
SP Energy Networks Documentation
Project Progress and Updates
- SPEN have started works at the village as of Monday 15th April and are on schedule. See photo below
- The team has also updated the phase plan to reflect council requests to avoid working on the main road at certain times. Updated on Website
- The team are due to come along to the Dirleton Village Association meeting at 7pm this Thursday and will talk through the project in person
Andrew and Chris attended the village meeting wanted to follow up with a couple of updates:
- Updated phase construction PDF attached
- PDF of slide presentation from the Dirleton village meeting